Back to projects

2018 Street Upgrading and Paving

St. Lawrence, Newfoundland and Labrador

completeHighways and RoadsSCF
Federal contribution
$176,843
Federal share24%

of $725.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2019
Built

Approved 16 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of St. Lawrence
Construction start
Aug 15, 2019(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2019
  • Construction end2.2 years earlyforecast Nov 30, 2021

Also in St. Lawrence

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52188 in the federal list. How to read these figures.