Back to projects

Mahaney's Lane Water, Sewer and Street Upgrading

Carbonear, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$71,144
Federal share29%

of $244.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Carbonear
Construction start
Sep 9, 2019(actual)
Construction end
Aug 31, 2020(actual)

Against the original forecast

  • Construction start15 months lateforecast May 30, 2018
  • Construction end8 months lateforecast Dec 31, 2019

Also in Carbonear

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52192 in the federal list. How to read these figures.