Back to projects

Watermain Ext Phase II

New-Wes-Valley, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$196,804
Federal share31%

of $634.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
20192020
Built

Approved 16 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of New-Wes-Valley
Construction start
Aug 1, 2019(actual)
Construction end
Sep 22, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2019
  • Construction end14 months earlyforecast Nov 30, 2021

Also in New-Wes-Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52205 in the federal list. How to read these figures.