Watermain Ext Phase II
New-Wes-Valley, Newfoundland and Labrador
Federal contribution
$196,804
Federal share31%
of $634.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
20192020
Built
Approved 16 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of New-Wes-Valley
- Construction start
- Aug 1, 2019(actual)
- Construction end
- Sep 22, 2020(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 1, 2019
- Construction end14 months earlyforecast Nov 30, 2021