Back to projects

Watermain Extension (Connect Newtown to Valleyfield)

New-Wes-Valley, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$453,309
Federal share50%

of $906.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of New-Wes-Valley
Construction start
Jul 3, 2018(actual)
Construction end
Nov 1, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 24, 2018
  • Construction end2 months earlyforecast Dec 31, 2018

Also in New-Wes-Valley