Connect water main to Newtown - New-Wes-Valley
New-Wes-Valley, Newfoundland and Labrador
Federal contribution
$341,353
Federal share40%
of $853.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of New-Wes-Valley
- Construction start
- Jul 17, 2020(actual)
- Construction end
- Oct 15, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2020
- Construction end8 weeks earlyforecast Dec 12, 2020
Also in New-Wes-Valley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53920 in the federal list. How to read these figures.