Booster Pump Upgrade on Pine Tree Road

Gambo, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$48,037
Federal share26%

of $181.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
201920202021
Built

Approved 16 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Gambo
Construction start
Oct 30, 2019(actual)
Construction end
Nov 30, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 1, 2019
  • Construction end13 months earlyforecast Dec 31, 2021