Water System Improvements Phase 4

Mainland, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$75,906
Federal share33%

of $231.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2018
2019
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Mainland
Construction start
Jul 30, 2019(actual)
Construction end
Sep 15, 2019(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 15, 2019
  • Construction end2 months earlyforecast Nov 15, 2019

Also in Mainland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52212 in the federal list. How to read these figures.