Water Supply Upgrades: Dam Liner

Mainland, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$65,851
Federal share40%

of $164.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
Built

Approved 23 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Mainland
Construction start
Oct 5, 2023(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2023
  • Construction end3 months earlyforecast Feb 28, 2024