Maple Street Reconstruction

Stephenville, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$305,807
Federal share29%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2018
2019
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Stephenville
Construction start
Jul 16, 2019(actual)
Construction end
Oct 15, 2019(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Nov 15, 2019

Also in Stephenville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52214 in the federal list. How to read these figures.