Grove street rehabilitation phase 2 St. Claire Street Reconstruction
Stephenville, Newfoundland and Labrador
Federal contribution
$887,035
Federal share26%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Stephenville
- Construction start
- May 27, 2017(actual)
- Construction end
- Jul 12, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2017
- Construction end6 months earlyforecast Dec 31, 2018