Grove Street Rehabilitation - Phase 2

Stephenville, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$808,560
Federal share48%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Stephenville
Construction start
May 9, 2017(actual)
Construction end
Jul 12, 2018(actual)

Against the original forecast

  • Construction end3 months lateforecast Mar 31, 2018

Also in Stephenville