Back to projects

Purchase and Installation of a Virtual Network and Storage Area Network (SAN)

St. John's, Newfoundland and Labrador

completePublic TransitPTIF
Federal contribution
$42,358
Federal share47%

of $90.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2018
2019
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of St. John's
Construction start
Mar 31, 2019(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 30, 2018
  • Construction end7 months lateforecast Nov 30, 2018

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52252 in the federal list. How to read these figures.