Confederation Trail

Stratford, Prince Edward Island

completeRecreationNRP
Federal contribution
$430,904
Federal share16%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
201920202021
Built

Approved 7 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Oct 6, 2020(actual)
Construction end
Jul 5, 2021(actual)

Against the original forecast

  • Construction start15 months lateforecast Jul 2, 2019
  • Construction end20 months lateforecast Nov 2, 2019