Victoria Park Expansion
Charlottetown, Prince Edward Island
Federal contribution
$1.3M
$1,283,333
Federal share33%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
20202021
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- May 6, 2019(actual)
- Construction end
- Jun 30, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Mar 25, 2019
- Construction end4 weeks lateforecast May 31, 2021