Massey Hall Revitalization
Federal contribution
$30.0M
$30,000,000
Federal share33%
of $91.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2018
201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- The Corporation of Massey Hall and Roy Thomson Hall
- Construction start
- Apr 24, 2018(actual)
- Construction end
- Oct 30, 2021(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 1, 2018
- Construction end13 months lateforecast Sep 30, 2020
Also in Toronto