Road infrastructure, Drinking water, wastewater and surface water

Moncton, New Brunswick

completeDrinking WaterSCF
Federal contribution
$460,807
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 17, 2018
20192020
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
University of Moncton
Construction start
Jul 2, 2019(actual)
Construction end
Oct 20, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2019
  • Construction end3 weeks lateforecast Sep 30, 2020