Back to projects

Increase in capacity of treatment plant

Sainte-Eulalie, Quebec

completeWastewaterCWWF
Federal contribution
$2.8M
$2,767,496
Federal share50%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2019
2019202020212022
Built

Approved 10 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 17, 2019(actual)
Construction end
Jun 22, 2022(actual)

Against the original forecast

  • Construction start16 months lateforecast Jun 4, 2018
  • Construction end7 months lateforecast Nov 30, 2021

Also in Sainte-Eulalie