Surface Transit Operational Improvement Studies - Phase 1

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$116,605
Federal share49%

of $236.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 23, 2018
20182019
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Oct 1, 2017(actual)
Construction end
Dec 14, 2018(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2019