Finch West Transportation Master Plan

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$437,918
Federal share36%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 23, 2018
201920202021
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Mar 1, 2018(actual)
Construction end
Nov 30, 2020(actual)

Against the original forecast

  • Construction end8 months earlyforecast Jul 31, 2021