Living Yonge

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$1.6M
$1,643,807
Federal share47%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 23, 2018
2018201920202021
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Sep 1, 2017(actual)
Construction end
Dec 23, 2020(actual)

Against the original forecast

  • Construction start12 months earlyforecast Sep 1, 2018
  • Construction end7 months earlyforecast Jul 31, 2021