Living Yonge
Federal contribution
$1.6M
$1,643,807
Federal share47%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 23, 2018
2018201920202021
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Dec 23, 2020(actual)
Against the original forecast
- Construction start12 months earlyforecast Sep 1, 2018
- Construction end7 months earlyforecast Jul 31, 2021
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52390 in the federal list. How to read these figures.