Installation of Cycling Facilities on Woodbine Ave.

Toronto, Ontario

completeActive TransportationPTIF
Federal contribution
$213,607
Federal share43%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 23, 2018
2017201820192020
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Jun 1, 2016(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction end6 months lateforecast Sep 30, 2019

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52394 in the federal list. How to read these figures.