Back to projects

Installation of Cycling Facilities on Lakeshore Blvd West

Toronto, Ontario

completeActive TransportationPTIF
Federal contribution
$410,878
Federal share34%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 23, 2018
201820192020
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Oct 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52395 in the federal list. How to read these figures.