Jerry Forbes Centre for Community Spirit - Renovation

Edmonton, Alberta

completeOtherCCRIS
Federal contribution
$1.8M
$1,799,600
Federal share40%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 8, 2018
2019
Built

Approved 8 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Apr 16, 2018(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction end6 months lateforecast Sep 1, 2018