North East Sector - Evergreen Reservoir
Federal contribution
$14.7M
$14,678,775
Federal share26%
of $56.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2019
201920202021202220232024
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Saskatoon
- Construction start
- Aug 16, 2021(actual)
- Construction end
- Mar 15, 2024(actual)
Against the original forecast
- Construction start6 months earlyforecast Feb 1, 2022
- Construction end7 months lateforecast Aug 10, 2023
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52549 in the federal list. How to read these figures.