Wastewater Treatment Plant Digester Tank 4
Federal contribution
$9.5M
$9,500,000
Federal share33%
of $28.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2019
2019202020212022
Built
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Saskatoon
- Construction start
- Aug 20, 2019(actual)
- Construction end
- Jun 29, 2022(actual)
Against the original forecast
- Construction start12 months earlyforecast Aug 21, 2020
- Construction end4 weeks lateforecast May 31, 2022
Also in Saskatoon