Wastewater Treatment Plant Digester Tank 4

Saskatoon, Saskatchewan

completeWastewaterNRP
Federal contribution
$9.5M
$9,500,000
Federal share33%

of $28.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2019
2019202020212022
Built

Approved 7 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Saskatoon
Construction start
Aug 20, 2019(actual)
Construction end
Jun 29, 2022(actual)

Against the original forecast

  • Construction start12 months earlyforecast Aug 21, 2020
  • Construction end4 weeks lateforecast May 31, 2022

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52550 in the federal list. How to read these figures.