Smart Bus Technology (Phase 2)
Federal contribution
$9.9M
$9,924,318
Federal share50%
of $19.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 16, 2018
today
20192021202320252027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Transit
- Construction start
- Nov 14, 2018(actual)
- Construction end
- Sep 30, 2026(forecast)
Against the original forecast
- Construction start6 weeks lateforecast Oct 1, 2018
Also in Undefined
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52555 in the federal list. How to read these figures.