Pierceland Wastewater Lagoon Expansion
Federal contribution
$1.1M
$1,050,626
Federal share33%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2018
20192020
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- SaskWater
- Construction start
- May 7, 2020(actual)
- Construction end
- Nov 17, 2020(actual)
Against the original forecast
- Construction start6 weeks lateforecast Mar 25, 2020
Also in Pierceland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52565 in the federal list. How to read these figures.