Village of Pierceland Wastewater Treatment Plant Upgrade
Federal contribution
$484,800
Federal share40%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 29, 2024
today
2024202520262027
BuiltForecast
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Pierceland
- Construction start
- Aug 1, 2026(forecast)
- Construction end
- Mar 31, 2027(forecast)
Also in Pierceland