Lagoon Expansion
Federal contribution
$504,179
Federal share18%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Redvers
- Construction start
- May 19, 2020(actual)
- Construction end
- Dec 15, 2020(actual)
Against the original forecast
- Construction end2.3 years earlyforecast Mar 31, 2023
Also in Redvers