Town of Redvers - Water Treatment Plant and Process Upgrade

Redvers, Saskatchewan

approvedDrinking WaterGIS
Federal contribution
$2.5M
$2,464,000
Federal share40%

of $6.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 29, 2024
today
2024202520262027
BuiltForecast

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Redvers
Construction start
Apr 1, 2026(forecast)
Construction end
Sep 30, 2027(forecast)