Wastewater Treatment System Upgrade

Val Marie, Saskatchewan

completeWastewaterSCF
Federal contribution
$757,242
Federal share31%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
2019202020212022
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Val Marie
Construction start
Nov 15, 2018(actual)
Construction end
Nov 15, 2021(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2022