Back to projects

Village of Val Marie - Landfill Decommissioning

Val Marie, Saskatchewan

underwaySolid Waste ManagementGIS
Federal contribution
$89,000
Federal share40%

of $222.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2022
2023202420252026
BuiltForecast

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Val Marie
Construction start
Dec 15, 2023(actual)
Construction end
Mar 31, 2026(forecast)

Also in Val Marie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63866 in the federal list. How to read these figures.