Water Treatment Plant Upgrade
Federal contribution
$648,422
Federal share32%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2018
20192020
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Ogema
- Construction start
- Dec 1, 2018(actual)
- Construction end
- Jun 30, 2020(actual)
Against the original forecast
- Construction end21 months earlyforecast Mar 31, 2022