Town of Ogema Wastewater Infrastructure Upgrades
Federal contribution
$1.1M
$1,125,200
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
202120222023202420252026
BuiltForecast
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Ogema
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Mar 31, 2026(forecast)
Also in Ogema
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57178 in the federal list. How to read these figures.