Lake Manitoba/Lake St. Martin Outlet Channels

Grahamdale, Manitoba

approvedDisaster MitigationDMAF
Federal contribution
$247.5M
$247,500,000
Federal share50%

of $495.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2018
2019202120232025
BuiltForecast

Approved 3 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
Province of Manitoba
Construction start
Jun 30, 2018(forecast)
Construction end
Mar 31, 2026(forecast)