Speed Curve at Little John's Road

Grahamdale, Manitoba

completeHighways and RoadsRNIS
Federal contribution
$45,616
Federal share75%

of $60.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2021
Built

Approved 6 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Feb 1, 2021(actual)
Construction end
Nov 26, 2021(actual)

Against the original forecast

  • Construction start3 months earlyforecast May 1, 2021
  • Construction end2 months earlyforecast Jan 31, 2022

Also in Grahamdale

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58385 in the federal list. How to read these figures.