Chipman Community Road, Water and Wastewater
Federal contribution
$581,493
Federal share60%
of $969.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 26, 2019
2019
Built
Approved 12 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Chipman
- Construction start
- Oct 1, 2018(actual)
- Construction end
- Nov 1, 2019(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 9, 2018
- Construction end13 months lateforecast Oct 9, 2018
Also in Chipman
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52641 in the federal list. How to read these figures.