Chipman Community Road, Water and Wastewater

Chipman, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$581,493
Federal share60%

of $969.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 26, 2019
2019
Built

Approved 12 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Chipman
Construction start
Oct 1, 2018(actual)
Construction end
Nov 1, 2019(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 9, 2018
  • Construction end13 months lateforecast Oct 9, 2018

Also in Chipman

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52641 in the federal list. How to read these figures.