Back to projects

Wastewater Treatment Facility Upgrade

Chipman, New Brunswick

completeWastewaterCWWF
Federal contribution
$748,653
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018201920202021
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Chipman
Construction start
Oct 19, 2020(actual)
Construction end
Jan 28, 2021(actual)

Against the original forecast

  • Construction start24 months lateforecast Nov 1, 2018
  • Construction end10 months lateforecast Mar 31, 2020

Also in Chipman