Wastewater Treatment Facility Upgrade
Federal contribution
$748,653
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
20172018201920202021
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Chipman
- Construction start
- Oct 19, 2020(actual)
- Construction end
- Jan 28, 2021(actual)
Against the original forecast
- Construction start24 months lateforecast Nov 1, 2018
- Construction end10 months lateforecast Mar 31, 2020
Also in Chipman
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48227 in the federal list. How to read these figures.