North Sewer System Upgrades - City of Yorkton
Federal contribution
$3.7M
$3,710,000
Federal share32%
of $11.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 26, 2019
20192020
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Yorkton
- Construction start
- Apr 11, 2019(actual)
- Construction end
- Oct 9, 2020(actual)
Against the original forecast
- Construction start3 weeks earlyforecast May 1, 2019
- Construction end6 weeks lateforecast Aug 31, 2020