City of Yorkton - Logan Green Pathway
Federal contribution
$331,063
Federal share40%
of $827.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Yorkton
- Construction start
- Aug 19, 2021(actual)
- Construction end
- Oct 24, 2022(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2022
Also in Yorkton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59326 in the federal list. How to read these figures.