Ben Calf Robe St. Clare School Replacement
Federal contribution
$5.2M
$5,200,000
Federal share23%
of $22.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2019
201920202021202220232024
Built
Approved 6 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Edmonton Catholic Separate School District No.7
- Construction start
- Sep 15, 2020(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Feb 3, 2020
- Construction end2 months lateforecast Sep 1, 2023
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52699 in the federal list. How to read these figures.