Back to projects

Ben Calf Robe – St. Clare School Replacement

Edmonton, Alberta

completeCultureCCRIS
Federal contribution
$5.2M
$5,200,000
Federal share23%

of $22.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2019
201920202021202220232024
Built

Approved 6 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Sep 15, 2020(actual)
Construction end
Oct 31, 2023(actual)

Against the original forecast

  • Construction start7 months lateforecast Feb 3, 2020
  • Construction end2 months lateforecast Sep 1, 2023

Also in Edmonton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52699 in the federal list. How to read these figures.