Toronto Region Ravine Erosion Risk Management and Hazard Mitigation
Federal contribution
$22.3M
$22,311,578
Federal share40%
of $55.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 3, 2019
today
20192022202520282031
BuiltForecast
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Toronto and Region Conservation Authority (TRCA)
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Mar 31, 2033(forecast)
Against the original forecast
- Construction start5 months lateforecast Jan 6, 2020
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52937 in the federal list. How to read these figures.