Jordantown-Acaciaville-Conway Betterment Association Community Centre

Digby, Nova Scotia

completeRecreationSCF
Federal contribution
$1.7M
$1,691,813
Federal share14%

of $11.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 30, 2018
2019202120232025
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 14, 2023(actual)
Construction end
Mar 18, 2025(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 19, 2023
  • Construction end4 months lateforecast Nov 29, 2024

Also in Digby

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52963 in the federal list. How to read these figures.