Compass Nova Scotia - Affordable Housing Retrofits
Federal contribution
$1.5M
$1,539,190
Federal share29%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 18, 2024
202320242025
Built
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Compass Nova Scotia Co-operative Homes Ltd.
- Construction start
- Aug 12, 2024(actual)
- Construction end
- Nov 14, 2025(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2024
- Construction end3 months lateforecast Aug 29, 2025
Also in Digby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66477 in the federal list. How to read these figures.