St. Malo Water Renewal

St. Malo, Manitoba

completeWastewaterSCF
Federal contribution
$333,333
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 2, 2019
20202021
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 24, 2020(actual)
Construction end
Jun 7, 2021(actual)

Against the original forecast

  • Construction start10 months earlyforecast Jun 21, 2021
  • Construction end6 months earlyforecast Nov 30, 2021

Also in St. Malo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52970 in the federal list. How to read these figures.