Water Treatment Plant

St. Malo, Manitoba

completeDrinking WaterCWWF
Federal contribution
$325,000
Federal share50%

of $650.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 1, 2016(actual)
Construction end
Nov 6, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 1, 2016
  • Construction end5 months earlyforecast Mar 31, 2018