Watson Lake New Public Works /Fire hall Combination building
Federal contribution
$7.1M
$7,113,697
Federal share71%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2019
2019202020212022
Built
Approved 8 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Watson Lake
- Construction start
- Aug 1, 2020(actual)
- Construction end
- Feb 24, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2020
- Construction end8 months earlyforecast Oct 30, 2022