Town of Watson Lake Construction Phase 1A Water, Sewer, and Road Upgrades
Federal contribution
$6.5M
$6,450,000
Federal share75%
of $8.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2023
2024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Watson Lake
- Construction start
- Aug 28, 2023(actual)
- Construction end
- Nov 27, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2023
- Construction end13 months earlyforecast Dec 15, 2025
Also in Watson Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67831 in the federal list. How to read these figures.