Whitehorse Operations Building Expansion

Whitehorse, Yukon

completeAdministration, Emergency and Public WorksSCF
Federal contribution
$8.0M
$8,025,000
Federal share75%

of $10.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 12, 2019
2019202120232025
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Whitehorse
Construction start
Sep 4, 2024(actual)
Construction end
Dec 19, 2025(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2024
  • Construction end7 months earlyforecast Jul 31, 2026