Whitehorse City Hall Energy Upgrade
Federal contribution
$3.8M
$3,750,000
Federal share75%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 12, 2019
today
20192021202320252027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Whitehorse
- Construction start
- Aug 1, 2025(actual)
- Construction end
- Oct 31, 2026(forecast)
Against the original forecast
- Construction start2 months earlyforecast Oct 1, 2025